(Photo courtesy of GTA)
(Tamuning, Guam) Tuesday, April 21, 2026- GTA continues islandwide restoration efforts following Typhoon Sinlaku, with significant progress across all services.
Network updates as of 3:30 p.m., April 21:
Wireless Network: 100% restored
Fiber & Air Fiber: 100% restored
Home Internet (DSL): 97% of customers connected
Remaining service interruptions are largely due to ongoing commercial power outages. As power is restored by the Guam Power Authority (GPA), connectivity is expected to continue improving. GTA teams and partners are working around the clock to complete restoration safely and efficiently.
Customers experiencing issues are encouraged to restart their devices. If problems persist, please contact GTA at 671-644-4482.
UPDATE AS OF 3:30PM, April, 21, 2026